Assign team resources
This topic describes how to assign team resources, and adjust team assignments from the team Demand tab.
In this topic:
- Prerequisites
- Assign resources to a resource request or promised allocation
- Promise an allocation
- Reject and forward a demand
- Adjust allocation of an assignment
- Remove an assignment or change its status
Prerequisites
To assign team resources to a resource request, you must meet the following requirements:
-
You must have the Edit Resource Pools or Edit All Resource Pools access grant.
-
You are the team manager, or the manager of its parent team.
-
The position specified your team in the Resource Pool column.
Assign resources to a resource request or promised allocation
You can assign resources in your team and its sub-teams to a resource request or a promised allocation.
Note: To assign a resource to a promised allocation:
-
You must have the Resource Mgmt: Promise Unspecified Resources access grant.
-
The parameter ENABLE_PROMISE_RESOURCE_ALLOCATION must be enabled.
To assign a resource to a position or a promised allocation:
-
Open your team and go to the Demand tab.
-
Do either of the following:
-
Select one or more resources to assign.
-
(Optional) Check the option Commit selected resources if you want to commit the selected resources after they are assigned.
This option appears only when the parameter
ENABLE_COMMIT_RESOURCES_IN_RESOURCE_FINDER
is set totrue
. If you want this option to be checked by default, set the parameterCHECK_COMMIT_RESOURCES_IN_RESOURCE_FINDER
totrue
in the Administration Console. -
(Optional) Check the option Distribute demand evenly to selected resources if you want to distribute the position's demand or the promised allocation evenly to the selected resources.
This option appears only when you select at least two resources and the parameter
ENABLE_DISTRIBUTE_RESOURCES_IN_RESOURCE_FINDER
is set totrue
. If you want this option to be checked by default, set the parameterCHECK_DISTRIBUTE_RESOURCES_IN_RESOURCE_FINDER
totrue
in the Administration Console.If you do not check this option, the allocated efforts of the resources are used in the order that the resources are selected. For example, if you select Elva and then select Johnson to assign to a position or promise, the allocation of Elva is used first.
-
Click anywhere on the Demand tab, or click OK if you are in the Select Resource(s) to Assign dialog box to save the changes.
Promise an allocation
You can promise an allocation without specifically naming the resource, and assign a specific resource at a later time.
To promise an allocation:
-
Prerequisites:
-
You must have the Resource Mgmt: Promise Unspecified Resources access grant.
-
The parameter
ENABLE_PROMISE_RESOURCE_ALLOCATION
must be enabled.
-
-
Open your team and go to the Demand tab.
-
Click ... next to the position to promise and select Promise.
A new line appears with Promise as the resource. The status defaults to Soft Booked and the promised allocation defaults to the position's unmet demand. You can edit the promised allocation value if needed.
-
Your changes are saved automatically.
Reject and forward a demand
If your team cannot fulfill a resource demand, you can reject the demand. You can also forward a demand to another team where this is a more suitable resource.
To reject a resource demand:
-
Open your team and go to the Demand tab.
-
Click ... next to the position to reject and select Reject.
The Reject request for unmet demand dialog box opens.
-
Provide a reason for rejecting the demand in the Comments field.
-
Click Done.
To forward a resource demand:
-
Open your team and go to the Demand tab.
-
Click ... next to the position to forward and select Forward.
The Forward request to another team dialog box opens.
-
Specify a team in the Forward to Team field.
-
Provide a reason for forwarding the resource demand in the Comments field.
-
Click Done.
Adjust allocation of an assignment
You can adjust the allocation of an assignment for Month or Week period types. For details, see Period type.
To adjust the allocation of an assignment:
-
Open your team and go to the Demand tab.
-
Editable assignments are marked with an Edit
icon. Locate the assignment you want to adjust.
-
Double-click the time period cell whose allocation you want to adjust and provide a new value.
Shortcuts when editing allocation
Arrow keys to move cursor
Press the Arrow keys to move your cursor to the right, left, previous line and next line. Enter
andEsc
keys to enter and exist Edit mode-
Place your cursor on a cell.
-
Press the
Enter
key to enter the Edit mode and make the changes. -
Press the
Enter
key to save the changes.Press the
Esc
key to discard the changes.
Shift
+ click to copy a cell value to the same line-
Click the cell whose value is to be copied.
-
Press the
Shift
key and at the same time click another cell on the same line.The cells in between are filled with the copied value.
Ctrl
+D
to copy a range down-
Select more than one line.
-
Press the
Ctrl
andD
keys at the same time.The values in the first line are copied to all the other lines down.
Ctrl
+C
andCtrl
+V
to copy cell values-
Select one or more cells whose values are to be copied.
-
Press
Ctrl
andC
. -
Select the cells that you want to copy the values to.
-
Press
Ctrl
andD
.
Delete values in multiple cells -
Select one or more cells whose values are to be deleted.
-
Press Delete.
-
-
Click anywhere on the page to save your changes.
Remove an assignment or change its status
When a resource (either a named resource or a promise) is assigned to a position, you can remove the assignment, or change its status.
To remove an assignment or change its status:
-
Open your team and go to the Demand tab.
-
To remove a resource or promise, click the Delete
icon next to it. The changes are saved automatically.
-
To change the assignment status, in the Status column of the resource or promise, select Committed or Soft Booked.
-
Click anywhere on the page to save the changes to the status.
See also: